Home > BUSINESS > ENGINEERING
ENGINEERING
Protection Relay Setting Calculation & Review
-
◎ Generator Protection Relay
◎ Transformer Protection Relay
◎ Transmission Line Protection Relay
◎ Bus Protection Relay
◎ Motor Protection Relay
◎ Feeder Protection Relay
-
◎ ABB
◎ GE
◎ Siemens
◎ Schneider
◎ SEL
-
|
Project |
Period |
Client |
|
|
154kV Biomass ECMS PJT |
2017.01 ~ 2018.01 |
Hyosung Co., Ltd |
|
|
154kV KOEN Yeongdong Division ECMS PJT |
2016.12 ~ 2016.12 |
Hyosung Co., Ltd |
|
|
154kV Chungju Hydroelectric Power Plant |
2016.10 ~ 2016.11 |
Hyosung Co., Ltd. |
|
|
154kV Yeongnam LNG Power Plant |
2016.05 ~ 2016.11 |
Hyosung Co., Ltd. |
|
|
154kV KDHC Heat Supply Facilities |
2015.11 ~ 2015.12 |
KDHC |
|
|
154kV Seomjingang Hydroelectric Power Plant |
2015.09 ~ 2016.06 |
LSIS Co., Ltd |
|
|
154kV Incheon airport energy co. LTD |
2015.08 ~ 2015.11 |
Incheon Airport Energy Co., Ltd |
|
|
154kV Osan Combined Heat & Power Plant |
2014.12 ~ 2015.04 |
Hyosung Co., Ltd. |
|
|
154kV Saemangeum Power Plant |
2014.11 ~ 2014.12 |
eTEC E&C Co., Ltd |
|
|
154kV Seo Incheon Thermoelectric Power Plant |
2014.05 ~ 2014.05 |
ABB Korea Co., Ltd |
|
|
154kV Ansan Combined Heat & Power Plant |
2014.04 ~ 2014.06 |
Kwangmyung Electric Co., Ltd |
|
|
154kV Hanam Combined Heat & Power Plant |
2014.04 ~ 2014.08 |
Nasan Electric Industries Co., Ltd |
|
|
154kV Incheon Airport Energy Prot. Relay |
2014.01 ~ 2014.02 |
Incheon Airport Energy Co., Ltd |
|
|
154kV Seo Incheon CCPP |
2013.05 ~ 2013.05 |
ABB Korea Co., Ltd |
|
|
154kV Sejong Happy City |
2013.03 ~ 2013.03 |
ABB Korea Co., Ltd |
|
|
154kV District Heating Sejong Happy City |
2013.01 ~ 2013.02 |
ABB Korea Co., Ltd |
|
|
22.9kV Samkwang Glass Nonsan, Cheonan Factory Energy Efficiency Project |
2018.01 ~ 2018.02 |
e tec E&S Co., Ltd |
|
|
22.9kV Gwangju-Jeonnam CES PJT |
2016.12 ~ 2016.12 |
ABB Korea Co., Ltd |
|
|
22.9kV Chuncheon Combined Heat & Power Plant PJT |
2016.07 ~ 2016.07 |
Hyosung Co., Ltd |
|
|
22.9kV Myeongji ECMS |
2016.04 ~ 2016.04 |
Hyosung Co., Ltd. |
|